1 | M/s. SUNDARAM FASTENERS LTD., DR. RADHAKRISHNAN SALAI, MYLAPORE, CHENNAI - 4. | Civil, structural, Land Development Mahindra world city - SEZ, Chengalpet. | 594 |
2 | M/s. SUNDARAM FASTENERS LTD., METAL FORMS DIVISION, HARITA, HOSUR. | Building construction for civil works | 108.69 |
3 | M/s. MARICO LIMITED Sp-15, PIPDIC ELECTRONICS PARK, THIRUBUVANAI, PONDICHERRY – 605 107. | Project 2K - Civil - Structural/ Road | 110 |
4 | HWPF DIVISION TVS- SFL KORKADU PONDICHERRY | Civil Works for Hot Forging Plant a) Internal Roads b) Power room c) Factory Building d) Raw Material Yard | 85.24 |
5 | ASCENT ENGINEERS 14/1, DEVADI STREET, MYLAPORE, CHENNAI - 600 004. | Construction of bus shelter & bus bay in NH45A - Bituminous Work. | 80.76 |
6 | TVS SUNDARAM FASTERNERS LTD., KORKADU VILLAGE, PONDICHERRY | General Civil works & Structural works New bay Expansion & Office buildings | 78.5 |
7 | FASTENERS DIVISION TVS- SFL KORKADU PONDICHERRY | Civil & Fabrication Works for Packing Plant and scrap yard | 63.42 |
8 | WHIRLPOOL OF INDIA LTD PONDICHERRY | Construction of Warehouse | 57 |
9 | LAKSHMI PVC PRODUCTS (P) LTD, ARIYAPALAYAM, PONDICHERRY | Construction of Factory shed | 49.98 |
10 | WHIRLPOOL OF INDIA LTD, THIRUBHUVANAI, PONDICHERRY. | Civil, structural works for sapphire area | 45.32 |
11 | TVS SUNDARAM FASTERNERS LTD., KORKADU VILLAGE,, PONDICHERRY | Construction of Warehouse & Methanol Storage Yard | 41.42 |
12 | WHIRLPOOL OF INDIA LTD PONDICHERRY | Construction of Warehouse a) Civil & Structural b) Road Work | 38.7 |
13 | LARSEN & TOUBRO LTD ECC DIVISION TLT & ROLLING MILL UNITS PONDICHERRY WORKS | Construction of Proto yard bay and construction of AUX. Galvanising plant at TLT works. | 36.48 |
14 | LARSEN & TOUBRO LTD ECC DIVISION TLT & ROLLING MILL UNITS PONDICHERRY WORKS | Construction of Compound wall at Sederapet. | 33 |
15 | TVS SUNDARAM FASTERNERS LTD., KORKADU VILLAGE, PONDICHERRY | a) Construction of Strom water drains, flooring and road work b) Scrap Yard and painting work. | 31.77 |
16 | TVS SUNDARAM FASTERNERS LTD., KORKADU VILLAGE, PONDICHERRY | a) Miscellaneous works such cooling tower, 1000LS Machine Foundation, Toilet Block Compound wall, Acid Tank, Lean to Roof, Aqua pond. b) Road Work and Construction of Drains, Loading Ramp and main gate. | 30.46 |
17 | OMEGA PACK, KODATHUR PONDICHERRY | a) Fire wood Boiler House b) Raw Material Shed c) Weigh bridge d) Approach Road | 27.73 |
18 | TVS SUNDARAM FASTERNERS LTD., KORKADU VILLAGE, PONDICHERRY | Construction of Rest Room Complex | 26.79 |
19 | TVS SUNDARAM FASTERNERS LTD., KORKADU VILLAGE, PONDICHERRY | Main Plant Expansion work | 26.46 |
20 | WHIRLPOOL OF INDIA LTD PONDICHERRY | Extension of EOU Work | 25.19 |
21 | WHIRLPOOL OF INDIA LTD PONDICHERRY | a) Construction of Temporary Warehouse b) Internal Road Work and Drains & ETP Road c) Construction of Sump Tank and Pump House for Fire hydrant system | 23.53 |
22 | OMEGA PACK KODATHUR PONDICHERRY | EOT Crane Shed | 20.5 |
23 | WHIRLPOOL OF INDIA LTD PONDICHERRY | Construction of Coil and Motor Storage Shed | 20.04 |
24 | LARSEN & TOUBRO LTD ECC DIVISION FORM WORK UNIT PONDICHERRY | Internal Bitumen Road | 19.41 |
25 | FASTENERS DIVISION TVS SFL KORKADU PONDICHERRY | a)Misc. Civil works in Canteen, Methanol tank yard, sludge bed, power room road, North side road, Various office rooms, overhead tank & bore well b)Construction of tool room & Garden pipe Line work. c)Miscellaneous Civil works such as scrap yard, Soak pit, rain water gutter, fencing work, fork lift yard, gym at rest room complex. | 15.98 |
26 | OMEGA PACK KODATHUR PONDICHERRY. | a) Construction of Boiler House & allied Civil Works b) Internal Road Work and Storm Water Drain | 14.91 |
27 | HINDUSTAN LEVER LIMITED, VADAMANKALAM. PONDICHERRY | Various civil works related to effluent treatment plant, NSD bar unit, temporary DG Room, Road Work, Scrap-bin, Welfare building and site developments. | 12.09 |
28 | B&R SOUTH PWD PUDUCHERRY | Improvements to the Nallavadu Road from RC.2(NH.45A) Pondicherry-Cuddalore road to Nallavadu Village in Ariyankuppam Commune, Puducherry. | 261.1 |
29 | PUBLIC HEALTH DIVISION,PWD PUDUCHERRY | Rehabilitation of Water Supply System in Zone-I Part-I (South) and Part-III (North) of Puducherry Town (Road Restoration). S/W: Rehabilitation of Water Supply System in Zone-I Part-I (South) and Part-III (North) of Puducherry Town (Road Restoration) - Phase-II. | 232.7 |
30 | B&R CENTRAL PWD PUDUCHERRY | Improvements and relaying of roads in Puducherry(Phase-I)Subwork: Improvements to the link road from RC-4 Valudavour road at Mettupalayam junction to NH66, Gorimedu, Puducherry | 211.8 |
31 | B&R CENTRAL PWD PUDUCHERRY | Improvements and relaying of roads in Puducherry.(Phase-I) SubWork:1.Improvements to the RC-14 Mill road from Venkata Subba Reddiar statue junction to Marapalam junction. 2.Improvements to Thengaithittu road from Cuddalore road junction to water tank in Mudaliarpet. 3.Improvements to link road from Uppalam road to Vambakeera palayam road. | 164.8 |
32 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road from Kalmandapam junction upto Malatar river bridge through Pandasozhanallur village in Nettapakkam Commune, Puducherry | 155 |
33 | B&R SOUTH PWD PUDUCHERRY | Improvements to the link road from T.V.Koil Chinnapet to Thirubuvanaipalayam village in Mannadipet Commune, Puducherry | 139.5 |
34 | B&R CENTRAL PWD PUDUCHERRY | Improvements to M.G. Road from Athithi Hotel to State border, Muthialpet, Puducherry. | 137.2 |
35 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road from Kizhur to Eripakkam State border in Nettapakkam Commune, Puducherry | 131.8 |
36 | B&R CENTRAL PWD PUDUCHERRY | Improvements and relaying of roads in Puducherry (Phase-I) Sub work1. Improvements to salai street at Muthialpet, Puducherry 2. Improvements to Vallalar salai from Anna salai junction to Kamaraj salai junction, Puducherry 3. Improvements to 45 feet bye pass road connecting venkata nagar and saram, Puducherry | 130.5 |
37 | B&R NORTH PWD PUDUCHERRY | Widening and Improvements to Thuthipet to Katterikuppam road in Thuthipet pet, Puducherry. | 117.7 |
38 | B&R SOUTH PWD PUDUCHERRY | Widening and improvements to the road from ECR junction up to Pudukuppam village ch.0/000 to 3/050 km in Bahour Commune, Puducherry. | 103.6 |
39 | B&R SOUTH PWD PUDUCHERRY | Improvements to the link road between RC.19 and RC.20 Via Pudukuppam and link road to Embalampet RC.19 Nettapakkam Commune, Puducherry. | 96.48 |
40 | B&R NORTH PWD PUDUCHERRY | Improvements to the Thethampakkam road branching from RC-4 Vazhudavour road leading to Suthukeny village in Mannadipet Commune, Puducherry. | 69.94 |
41 | B&R CENTRAL PWD PUDUCHERRY | Improvements to Lalbahadhur Sastri street from beach road to Anna Square, Puducherry. | 64.57 |
42 | B&R CENTRAL PWD PUDUCHERRY | Improvements to Lalbahadhur Sastri street from beach road to Anna Square, Puducherry. | 64.57 |
43 | PTDC, PUDUCHERRY | Improvements to the road leading to the Arts & Crafts Village from ECR at Murungapakkam, Puducherrry. | 55.47 |
44 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road RC.30 link road from Eripakkam State border to Sooramangalam junction at RC.21 in Nettapakkam Commune, Puducherry. | 53.4 |
45 | B&R SOUTH PWD PUDUCHERRY | Improvements to the Pangur main road from Pangur school to road connecting at Ariyur Sivaranthagam road via Erikarai in Villianur Commune, Puducherry. | 51.38 |
46 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road RC18 from Aranganur State Border to Aranganurpet in Bahour Commune, Puducherry | 44.23 |
47 | SLUM CLEARANCE BOARD, PUDUCHERRY | Remetalling and Black Topping to the internal roads at Amaithi Nagar, Oulgaret Municipality, Puducherry | 40.43 |
48 | B&R NORTH PWD PUDUCHERRY | Improvements to the Koodapakkam village road branching from Pathukannu Junction and connecting RC.12 Sanniyasikuppam road in Villianur Commune, Puducherry. | 40.07 |
49 | B&R NORTH PWD PUDUCHERRY | Widening and Improvements to the road from Kalmedupet junction to AFT culvert at RC.4 Valudavour road Ch.7/180 to 7/530km Oussudu Constituency, Puducherry. | 35.53 |
50 | B&R CENTRAL PWD PUDUCHERRY | Widening of the road in Maraimalai Adigal Salai at South side from Anna Statue to Uppar bridge, Puducherry. | 28.45 |
51 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road from Kanniakoil junction of ECR to Koravallimedu in Bahour Commune, Puducherry | 28.2 |
52 | B&R NORTH PWD PUDUCHERRY | Improvements to the left out portion of RC.13 Vadhanur road from Ch.6/200 to 7/200km. in Mannadipet Commune, Puducherry. | 27.77 |
53 | B&R SOUTH PWD PUDUCHERRY | Urgent permanent restoration for Madavethi South / West and Mary street at Bahour in Bahour Commune, Puducherry. | 27.48 |
54 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road from Ambedkar Statue to Pudupet(Chinnapet) Manamedu in Nettapakkam Commune, Puducherry. | 27.33 |
55 | B&R SOUTH PWD PUDUCHERRY | Urgent restoration to the RC-17 road from Odiampet village to PWD Pumphouse (Near Animal Husbandary Hospital) in Villianur Commune, Puducherry. | 27.14 |
56 | B&R SOUTH PWD PUDUCHERRY | Improvements to the road leading to Chinnaveerampattinam from Kakayanthope in Ariyankuppam Commune, Puducherry. | 26.08 |
57 | B&R SOUTH PWD PUDUCHERRY | Urgent permanent restoration for Madavethi North / East street at Bahour in Bahour Commune, Puducherry. | 23.92 |
58 | B&R SOUTH PWD PUDUCHERRY | Improvements to the Kanuvapet and church street junction at RC-17 Odiampet road in Villianur Commune, Puducherry. | 23.9 |
59 | B&R NORTH PWD PUDUCHERRY | Improvements at Pillaiyarkuppam and Sellipet road junction near Sankaraparani river bridge, Puducherry. | 20.34 |
60 | OULGARET MUNICIPALITY, PUDUCHERRY | Improvements to the link road connecting from Tindivanam road to Kamaraj Nagar at Gorimedu. | 20.12 |
61 | B&R NORTH PWD PUDUCHERRY | Providing BM and SDBC to the WBM road at Uruvaiyar Village, Selva Nagar Bolo Sai Baba Temple in Mangalam Constituency, Puducherry. | 19.07 |
62 | B&R NORTH PWD PUDUCHERRY | Improvements and attending patches RC-4 Valudavour road from Ousteri Boat Bouse to Pathukannu junction from CH.10/600 to 12/670Km, Puducherry. | 14.55 |
63 | B&R NORTH PWD PUDUCHERRY | Attending patches and improvements to RC-13 Sellipet road from Ch.1/100Km (Ammanankuppam village road) to Ch.2/200Km near Sellipet Bridge, Puducherry. | 14.37 |
64 | B&R NORTH PWD PUDUCHERRY | Urgent repairs to the Puliansalai road from Ch.0/050 to 0/470 in Ramanathapuram Village, Villianur Commune, Oussudu Constituency, Puducherry. | 14.26 |
65 | B&R NORTH PWD PUDUCHERRY | Improvements to the RC-13 Sellipet road from Thirumangalam Pathai to Vadhanur junction connecting RC-21 frontier road (Ch.7/200 to 7/980) in Mannadipet Commune, Puducherry | 14.2 |
66 | B&R SOUTH PWD PUDUCHERRY | Urgent repairs to the damaged road riding surface in connection RC-21 road from RC-30 Sooramangalampet to Molapakkam Village in Nettapakkam Commune, Puducherry. | 13.96 |
67 | B&R NORTH PWD PUDUCHERRY | Urgent repairs to the Puliansalai road from Ch.0/470 to 0/884 in Ramanathapuram Village, Villianur Commune, Oussudu Constituency, Puducherry. | 13.38 |
68 | B&R SOUTH PWD PUDUCHERRY | Urgent Improvements to the approach road from Kumandanmedu to low lying bridge at Thenpennaiyar River in Bahour Commune, Puducherry. | 13.24 |
69 | NATIONAL HIGHWAYS DIV, PWD, PUDUCHERRY | Providing paved shoulders on the Southern side of NH45A between Ch.34/870 and Ch.35/330 in Puducherry. | 13.2 |
70 | B&R NORTH PWD PUDUCHERRY | Improvements to Kalathumettupathai from Kozhuveri road junction to Mathur junction behind PIMS Hospital (Ch.2/268 to 3/537km), Puducherry. | 12.53 |
71 | B&R SOUTH PWD PUDUCHERRY | Urgent repairs to the Easwaran Koil Street road at Maducarai village in Nettapakkam Commune, Puducherry. | 11.43 |
72 | B&R SOUTH PWD PUDUCHERRY | Urgent repairs to the road branching from Pudukuppam road to Utchimedupet ch.0/400 to 0/850km in Bahour Commune, Puducherry. | 9.73 |
73 | B&R SOUTH PWD PUDUCHERRY | Urgent repairs to the road branching from Pudukuppam road to Utchimedupet ch.0/000 to 0/400km in Bahour Commune, Puducherry. | 9.65 |
74 | B&R SOUTH PWD PUDUCHERRY | Urgent repairs to the road branching from Pudukuppam road to Utchimedupet ch.0/850 to 1/250kmin Bahour Commune, Puducherry. | 8.53 |
75 | WHIRLPOOL OF INDIA LTD THIRUBHUVANAI PONDICHERRY. | Construction of Compound wall | 43.52 |
76 | WHIRLPOOL OF INDIA LTD THIRUBHUVANAI PONDICHERRY. | Construction of Road Work | 38.2 |
77 | WHIRLPOOL OF INDIA LTD THIRUBHUVANAI PONDICHERRY. | Construction of Compound wall | 22.55 |
78 | WHIRLPOOL OF INDIA LTD THIRUBHUVANAI PONDICHERRY. | Construction of Compound wall | 22.33 |
79 | WHIRLPOOL OF INDIA LTD THIRUVANDARKOIL PONDICHERRY. | Factory Building Work (118.14 x 36.8) | 372.8 |
80 | PUBLIC HEALTH DIVISION, PWD, PUDUCHERRY | Augmentation of water supply system for JJ Nagar, Annai Theresa Nagar, Nanbargal Nagar, Kamban Nagar, Vayalveli Nagar, Chellampappu Nagar, Mariyal Nagar, Deva Nagar and surrounding areas in Zone-IX, Puducherry (Distribution main, Pumping main, Road restoration and allied works). S/W: Providing and laying, distribution grid, pumping main and road restoration for Top Decker command area of OHT in Oulgaret School Campus, Puducherry. | 381.2 |
81 | IRRIGATION DIVISION, PWD, PUDUCHERRY | | 855.5 |
| | Construction of Check Dam across the River Sankaraparani at Chettipet Village in Mannadipet Commune, Puducherry. | |
| | | |
82 | WHIRLPOOL OF INDIA LTD THIRUBHUVANAI PONDICHERRY. | Construction of Warehouse | 905 |